Crossover Boulevard Road

Portfolios

Winchester, VA

Project Description

Construction of one mile of new paved roads with 321 lf bridge over I-81 and 2 lane roundabout. The project involves coordination of utilities, maintenance of traffic at both I-81 bridge crossing and Rt. 522 tie in. Project includes import of over 300,000 tons of select material type 1 and installation of 9,000 lf storm sewer piping. Also includes water line, concrete curbing and asphalt pavement. Project ties into the Tevis Street project that Perry completed in 2018 for the City of Winchester.

Reference

Frederick County Dept. of Public Works

Snowden Bridge Boulevard Extension

Portfolios

Stephenson, VA

Project Description

Construction of approximately 1 mile of paved road with a bridge that is 126 feet in length. The bridge crosses CSX railroad line. Includes coordination of major utilities (ie overhead power lines, jack/bore water line under railroad). Grading of approximately 75,000 cy including rock removal and sinkhole remediation. Utility work consists of 3,300 lf of storm sewer and 5,500 lf of water main. Curbing and asphalt trail follow the roadway.

Reference

Frederick County Department of Public Works

Trex Building 6

Portfolios

Winchester, VA

Project Description

Sitework for new 181,000 sf building. Project consists of removing rock along shored walls for partial underground building, underground utilities including conduit system for relocating existing overhead power lines, site concrete and asphalt paving.

Reference

Howard Shockey

Graystone Industrial Center – Phase 1

Portfolios

Winchester, VA

Project Description

Grading of 40 acres for industrial park storm water pond and 240,000 sf of building. Very rocky site. Work also includes underground utilities, site concrete, asphalt and concrete paving.

Reference

Howard Shockey

Graystone Building 3

Portfolios

Winchester, VA

Project Description

210,000 sf warehouse building in same complex we did buildings 1 and 2 for same client. Project includes large storm sewer bypass line to divert run off water thru site. Project includes 4,400 lf of storm sewer. Typical warehouse construction including sanitary, water, concrete paving and asphalt paving.

Reference

Howard Shockey

Hope Drive Expansion

Portfolios

Winchester, VA

Project Description

Construction of Hope Drive between Valley Avenue and Pleasant Valley Road. Includes new asphalt road, site concrete, storm, sanitary and water lines, new traffic signal, street lighting, landscaping, tunneling under railroad. Work to be done while maintaining traffic flow in the area.

Reference

City of Winchester

Hackwoods – Phase 1

Portfolios

Winchester, VA

Project Description

Sitework for 10 retirement villas on a 21-acre site. Done in 2 phases. Work includes site grading, underground utilities – storm, sanitary and water, site concrete, asphalt paving and restoration. Site is very rocky and will include extensive mass blasting and hoe ramming to obtain grades.

Reference

Warfel Construction