Project Description:  Sitework for new 181,000 sf building.  Project consists of removing rock along shored walls for partial underground building, underground utilities including conduit system for relocating existing overhead power lines, site concrete and asphalt paving.  

Start Date:  October, 2019

Scheduled Completion:  December, 2020

Contract Amount: $5,836,654

Percent Complete: 85%