Project Description:  Sitework for 80,000 sf athletic building including undercut and backfill of existing fill area within building pad, grading, rock removal, underground utilities, bioretention basins, site concrete and paving.  Project received an ENR award for the Best Athletic Facility in the mid-Atlantic United States.

Start Date:  September, 2016   

Completion:  December, 2017

Contract Amount:  between $2,000,000 and $2,500,000

Engineer:   Greenway Engineering