Project Description: Construction of a right-turn lane on ex. road, reconfiguration of an intersection, modification to several business entrances, installation of new traffic signal at reconfigured intersection, installation of new stormwater infrastructure including a BMP facility and site restoration. This work will be performed on a major road thru Winchester so traffic control will be very important.
Start Date: June, 2014
Scheduled Completion: December, 2014
Contract Amount: $1,945,020
Engineer: Greenway Engineering
Reference:
Shenandoah University
Physical Plant Office, Shingleton Building
1460 University Drive
Winchester, Va 22601
Phone: 540-665-4543
Contact: Barry Schnoor